Campus Way Finding and Signage - Phase 2

Beginning Thursday, Oct. 10 and continuing through Friday, Oct. 11, contractors will be installing concrete foundations for new signage at five locations throughout the campus vicinity.


The campus community can expect the following:

--Work will take place at 55th & Cottage Grove, 60th & Cottage Grove, 58th & Dorchester, 61st & Dorchester and 59th & Blackstone.

--The work will take place between 8 a.m. and 4 p.m. and will be noisy at times.

--Work includes one day to frame each site and a second day to pour concrete, weather permitting.

For questions, contact Jim Garcia, project manager, at 773.834.1825 or jgar@uchicago.edu or Gavin Tun, director-project management at 312.607.6654, or gavin1@uchicago.edu

Thank you for your patience.

Click here for a map showing the location of work.