Main Quadrangle paver restoration
Please be aware that paver restoration in the main quadrangle will commence Saturday, September 15, 2012. The campus community can expect the following:
--Damaged pavers will be removed and replaced in the main quadrangle
--Pavers will be leveled in areas of settlement
--Pedestrian access will be routed around the work areas
--Fencing will be placed around work areas as shown below
--Work is scheduled from September 15, 2012 through September 19, 2012
Click here for a map showing the location of work.
Please direct any questions to Jose Lopez, Sr. Project Manager, Facilities Services (jlopezjr@uchicago.edu, 773.834.8938) or Kevin Ahn, Client Services Manager, Facilities Services (kahn2@uchicago.edu, 773.702.5722). Thank you for your patience during this work.