Midway Plaisance Restoration
Location: Midway Plaisance and Ellis Avenue (East and West Sidewalks)
Date: March 19, 2012 March 30, 2012
Please be aware that concrete and lighting restoration will occur at the Midway Plaisance from March 19 March 30, 2012. The campus community can expect the following during this work:
--Work will be performed on the east and west sidewalks of Ellis Avenue
--Broken lighting bollards and damaged concrete sections will be restored
--Fencing will be placed around the work area
--A portion of the sidewalks will be closed but access will remain open throughout the project
--The work will be noisy at times
--Working hours are from 8:00am 5:00pm
--All areas will be restored upon completion
If you have any questions or concerns regarding this work, please contact Peter Hickling, Electric Shop Supervisor at (773) 834-1430 or Kevin Ahn, Client Services Manager at (773) 702-5722.
Thank you for your patience.